PMP美国项目管理模拟样题3
文章作者 100test 发表时间 2007:01:15 17:10:22
来源 100Test.Com百考试题网
1.You are a project manager for Waterways Houseboats, Inc. You’re been asked to perform a benefit/cost analysis for two proposed projects. Project A costs $2.4 million with potential benefits of $12 million and future operating costs of $3 million. Project B costs $2.8 million with potential benefits of $14 million and future operating costs of $2 million. Which project should you recommend? A. Project A because the cost to implement is cheaper than Project B B. Project A because the potential benefits plus the future operating costs are less in value than the same calculation for project B C. Project B because the potential benefits minus the implementation and future operating costs are greater in value than the same calculation for Project A D. Project B because the potential benefits minus t 下一页:阅读《PMP美国项目管理模拟样题3》的全文
|