PMP美国项目管理模拟题精选8
文章作者 100test 发表时间 2007:01:15 17:12:45
来源 100Test.Com百考试题网
Qustions 1: The output of scope change control consists of-- a. Scope changes, corrective action, and lessons learned b. Corrective action, scope changes, and project plan 0updates c. Performance measurement, additional planning, and lessons learned d. Work results, product documentation, and formal acceptance
Qustions 3:
The scope statement-- a. Dose not include project objectives such as cost, schedule, or quality measures b. Includes a description of project assumptions and constraints c. Provides a documented basis for preparing the PERT/CPM network d. Describes how the WBS will be structured
Qustions 5:
To relate the functional organizations to the WBS elements, the project manager should use a--
a. WBS index b. Project WBS c. Cost account matrix d. Work package assignment idex
Qustions 2: All the following are project 0selection methods except--