Qustions 1: 1. In a weak matrix organization, functional managers are usually responsible for:
Monitoring personnel performance Approval for changes to the project schedule Monitoring their project team member’s deliverables Changes that impact their team member~ participation
Qustions 3:
You are one of four full-time project managers in an organization You all sbare an administrative person There are generally 8-10 projects per year tbat involve about 25% of the organization~enployees, however, these employees do not report to you. Your organization can best be classified as:
Functional Strong matrix Projectized Balanced matrix
Qustions 5:
You have been promoted to Manager, Continuous Process Improvement. Your new position:
Is a project because the work will be performed by people Is not a project because Continuous Process Improvement will continue indefinitely Is a project because it is const 下一页:阅读《砺志PMP模拟题本周精选15》的全文
|