According to McGregor, a manager who uses Theory X sees workers as--

a. Highly motivated,willing to take responsibility, and reliable
b. Highly untrustworthy, needing to be watched and closely managed at all times
c. Very productive when first given an assignment
d. Unproductive at first, followed by periods of high productivity

Qustions 3:

A Project management information system comprises--


a.
IAny of the project management software used for schedule development
b. All the requited reports to be prepared on the project, who receives each one, and the method of distribution
c. The policies and procedures to follow as the project is performed
d. The tools and techniques used to gather, integrate, and disseminate the output of the other project management processes

Qustions 5:

The Project plan should be distributed to--

a.All stakeholders in the performing organization
b. All project stakeholders
c. Project team members and the project sponsor
d. Those people defined in the communication management plan

Qustions 2:
Although an output of the various control processes, corrective action is also an input to project plan execution because it--

a. Ensures that project objectives are met
b. Expedites actions to ensure that activities are completed on time
c. Completes the feedback loop needed to ensure effective project management
d. Involves performing a planned reponse for a specific project risk event

Qustions 4:

A change control board is --


a. Recommended for use on all projects, large or small
b. Used as required to approve or reject change requests
c. Managed by the project manager who serves its secretare
d. Composed of key members of the project team

Qustions 6:

Leadership and management are both necessary on projects. One definition of managing is that it involves producing key results expected by stakeholders, whereas leadership involves --

a.
Establishing direction, aligning people, and motivating and inspiring others
b.
Getting things done through other people
c.
Using charismatic power to motivate others to be productive
d.
Using all types of power, as appropriate, as motivational tools