PMP认证考试试题精选(6.1)

文章作者 100test 发表时间 2007:01:15 18:51:41
来源 100Test.Com百考试题网


1. The subdivision of major project deliverables, as identified in the scope statement, into smaller, more manageable components is called:
a. parametric estimation.
b. scope definition.
c. feasibility analysis.
d. benefit-cost analysis.

2. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called:
a. strategic planning.
b. alternative objectives inventory.
c. management by objectives.
d. contingency planning.

3. A fundamental tenet of modern quality management holds that quality is most likely to be achieved by:
a. planning it into the project.
b. developing final inspections for quality.
c. striving to do the best job possible.
d. conducting quality circle activities.

4. The time-phased budget that will be used to measure and monitor cost performance in he project is called the:
a. work breakdown structure.
b. project schedule.
c. cost baseline.
d. cost budget.

5. At XYZ Inc., the hourly wage for semi-skilled workers is .00. The annual audit shows that fringe benefits cost 30% of basic wages, and that overhead costs are 60% of wages plus fringe benefits. What is the “loaded” hourly wage for a semi-skilled worker at XYZ Inc.?
a. .40.
b. .60.
c. .12.
d. .33.

6. When there is uncertainty associated with one or more aspects of the project, one of the first steps to take is to:
a. revise project plan.
b. conduct a risk-benefit analysis.
c. conduct a needs analysis.
d. increase the estimated cost.

7. A narrative description of products or services to be supplied under contract is called:
a. the project plan.
b. a statement of work.
c. an exception report.
d. Pareto analysis.

8. An example of scope verification is:
a. reviewing the performance of an installed software module.
b. managing changes to the project schedule.
c. decomposing the WBS to a work package level.
d. performing a benefit/cost analysis to determine if the project should proceed.

9. All of the following are examples of a source of scope change except:
a. a variation in government regulations.
b. failure to include a required feature in the design of a telecommunication system.
c. discovering a need to engage in bottom-up cost estimating.
d. introducing technology that was not available when scope was originally defined.


相关文章


PMP认证考试试题精选(6.4)以及答案
PMP认证考试试题精选(6.3)
PMP认证考试试题精选(6.2)
PMP认证考试试题精选(5)以及答案
PMP认证考试试题精选(6.1)
PMP认证考试试题精选(4)以及答案
施工企业工程项目部的建设浅论
浅谈评标方法的发展变化及对公路工程建设的影响
风沙地区公路路基施工要求
澳大利亚华人论坛
考好网
日本华人论坛
华人移民留学论坛
英国华人论坛