Project Time Management

(Level of difficulty: 6 / 10)

Activity Definition

- Remember the sequence, activity definition come first

Activity Sequencing

- differences between PDM, ADM, Gnatt, PERT &. GERT etc

- could be confusing , take note!

Activity Duration Estimating

- must know how to calculate Critical Path

- remember Milestone is without duration

Schedule Development

- differences between crashing and fast tracking

- remember adding resources will not necessary help

- must know free/ total float, slack and lag

- what is a dummy activity?

- understand Monte Carlo analysis

Schedule Control

- what is variance analysis?