Qustions 1:
Which statement about customer expectations is not true --

a. The product or service should be usable as intended.
b. Contractual provisions, including schedule and performance standards, should be met.
c. Changes should be made immediately, and all customer wants should be satisfied without bureaucratic hassle
d. The seller should assume the responsibility of understanding customer needs and addressing them effectively.

Qustions 3:

The document that describes the objectives, work content, deliverables, and end product of a project is the--

a. Project charter
b. Product description
c. Scope statement
d. WBS&.nb
sp.

Qustions 5:

Maintenance is crucially important to projects and should--

a. Be included as an activity to be performed during the closeout phase
b. Have a separate phase in the life cycle in information systems projects because 60% to 70% of life-cycle costs of computer systems are generally devoted to maintenance
c. Not be viewed as part of the project life cycle
d. Always be viewed as a separate project

Qustions 2:
The WBS is an input to scope change control because it--

a. Provides information on project objectives
b. Defines the project’s scope baseline
c. Defines all project baselines
d. Provides informat
ion on scope performance

Qustions 4:

When an organization chooses a project 0selection model, the most important criterion is --

a. Capability
b. Realism
c. Ease of use
d. Cost

Qustions 6:

A project manager’s company operates in a high-technology area requiring the integration and sharing of several functional specialties. The project manager is considering the appropriate organizational structure ofr a new project, the likely choice would be --

a. Matrix
b. Tight matrix
c. Functional
d. Projectized

相关文章


PMP美国项目管理认证模拟题精选7
PMP美国项目管理认证考试的模拟题精选10
深圳代建制拟在全国交通行业推行
PMP美国项目管理认证考试模拟题精选6
天津:推出住房公积金与中德住房储蓄组合贷款
宏观调控“三管齐下”如投资仍过热将会再度加息
PMI-PMPExamTipsandNotes10
澳大利亚华人论坛
考好网
日本华人论坛
华人移民留学论坛
英国华人论坛