项目时间管理(中英文对照)
文章作者 100test 发表时间 2007:01:15 18:32:22
来源 100Test.Com百考试题网
Project Time Management includes the processes required to ensure timely completion of the project. Figure 6-1 provides an overview of the following major processes:
项目时间管理包括确保项目按时完成所必须的过程。图6-1概括了下面的主要过程。
6.1 Activity Defination—identifying the specific activities that must be performed to produce the various project deliverables.
工序定义-确定为完成各种可交付成果所必须进行的具体工序。
6.2 Activity Sequencing—identifying and documenting interactivity dependencies.
工序排序-确定工序之间的依赖关系,并形成文件。
6.3 Activity Duration Estimating—estimating the number of work periods which will be needed to complete individual activities.
关系工期评估-评估完成单个关系所需的工作时间的数量。
6.4 Schedule Development—analyzing activity sequences, activity durations, and resource requirements to create the project schedule.
编制进度计划-分析工序顺序、工序持续时间和资源需求。
6.5 Schedule Control—controlling changes to the project schedule.
进度控制-控制项目进度的变更。