81. You have had your Scope Definition approved and are working on your budget and schedule. In order to estimate the labor costs and the schedule you need to know who your team members are, and what their skill level is. You consult your staffing managenrnt plan and your staffingpool escription By following the recruitment practices and working with the procurement department to negotiate for arious external contractors you are able to complete a project directory. All these are steps in what process?
A. Organizational Planning
B. Resource Planning
C. Team Development
D. Staff Acquisition

82.The primary conmunication skills you will use in working with members of your project team will be:
A. Problem solving
B. Negotiating
C. Team building
D. Public relations

83.The primary conmunication skills you will use in working with your project sponsor will be:
A. Problem solving
B. Negotiating
C. Team building
D. Public relations

84.The primary conmunication skills you will use in working with functional managers will be:
A. Problem solving
B. Negotiating
C. Team building
D. Public relations

85.The primary conmunication skills you will use in working with external stakeholders will be:
A. Problem solving
B. Negotiating
C. Team building
D. Public relations

86.According to A H. Maslow, people~ needs must be satisfied according to a certain hierarchy.The order in which needs must be satisfied is:
A. Self-actualization, esteem, social, safety, physiological
B. Physiological, seW-actualization, social, esteem, safety
C. Physiological, safety, social, esteem, self-actualization
D. Self-actualization, social, physiological, safety, esteem

87.According to C. P. Alderfer, people~ needs fall into three broad categories. Which of the following is not one of Alderfer抯 categories?
A. Existence needs
B. Identity needs
C. Relatedness needs
D. GroMh needs

88.Your project plan requires personnel to wear a Radiation Monitor counter at all times while they are within the protected area surrounding a nuclear reactor. This requirement arises from your concern for:
A. Quality assurance reporting requirenrnts
B. Personnel safety needs
C. Stakeholder reporting requirements
D. Personnel physiological needs

89.A staffing management plan includes all of the following except:
A. Determining how to bring team members onto the project
B. A resource histogram
C. Determining how to release team members from the project
D. Documentation on who has the authority to make decisions

相关文章


项目管理知识:项目管理的沟通管理
PMP认证考试试题精选(6.4)以及答案
PMP认证考试试题精选(6.3)
PMP认证考试试题精选(6.2)
PMP认证考试试题精选(5)以及答案
PMP认证考试试题精选(6.1)
PMP认证考试试题精选(4)以及答案
施工企业工程项目部的建设浅论
浅谈评标方法的发展变化及对公路工程建设的影响
澳大利亚华人论坛
考好网
日本华人论坛
华人移民留学论坛
英国华人论坛