61. At what point inthe project is there the most risk of project failure?
A. Close out
B. Development
C. Implementation
D. Concept

62. Phase exits, kill points and stage gates are used for what purpose?
A. Planning the next stage in the project
B. Communicating milestones to stakeholders
C. Determining if the project should continue into the next phase
D. Measuring earned value

63. A complex project will fit best in what type of organization?
A. Functional
B. Cross-functional
C. Matrix
D. Balanced

64. Which knowledge area involves organizational theory as a tool/technique?
A. Communications Management
B. Cost Management
C. Risk Management
D. Human Resource Management

65. Human Resource Managenrnt is tightly linked to which other knowledge area?
A. Cost Management
B. Risk Management
C. Communications Management
D. Time Management

66. Which of the following is not considered a constraint in Organizational Planning?
A. Recruitment practices
B. Collective bargaining agreenrnts
C. Preferences of the project management team
D. Expected staff assignments

67. Outputs from Organizational Planning include all of the following except:
A. Staffing Management Plan
B. Organization Chart
C. Project Team Directory
D. Role and Responsibility Matrix

68. Inputs to Staff Acquisition include all of the following except:
A. Staffing Management Plan
B. Resource Histogram
C. Staffing pool description
D. Recruitment practices

69. Which of the following is not an input to Team Development?
A. Project Plan
B. Staffing Management Plan
C. Performance Reports
D. Reward and recognition systems

70. Cost Budgeting is defined as:
A. The estimated total cost of the project when done
B. Allocating the cost estimates to the individual work items
C. Estimating the cost of the resources needed to complete project activities
D. The sum of the approved cost estimates

71. The cost baseline is an output of what process?
A. Cost planning
B. Cost estimating
C. Cost budgeting
D. Cost control

72. The time phased budget that is used to measure and monitor cost performance is:
A. The project budget
B. The cost budget
C. The cost baseline
D. The cost estimate

相关文章


PMP认证考试试题精选(6.3)
PMP认证考试试题精选(6.2)
PMP认证考试试题精选(5)以及答案
PMP认证考试试题精选(6.1)
PMP认证考试试题精选(4)以及答案
施工企业工程项目部的建设浅论
浅谈评标方法的发展变化及对公路工程建设的影响
风沙地区公路路基施工要求
雨季现场施工安全措施
澳大利亚华人论坛
考好网
日本华人论坛
华人移民留学论坛
英国华人论坛